What are the valid NEXT steps to prepare for guest migration to new infrastructure? (Select two)

Sharpen your skills for the CompTIA Cloud+ (CV0-003) exam. Explore flashcards, multiple choice questions with hints and explanations, ensuring you're well-prepared for success!

When preparing for a guest migration to new infrastructure, several important steps should be taken to ensure a smooth transition. The correct next steps in this context include tagging the live migration VLAN on the trunk to the new servers as well as correctly sizing and provisioning NFS LUNs on the new storage.

Tagging the live migration VLAN on the trunk to the new servers is essential because it ensures that the data traffic for the migration is appropriately routed and segregated from other types of traffic. This allows for a seamless migration process, where virtual machines can move from the old infrastructure to the new infrastructure without interruptions or network-related issues.

Correctly sizing and provisioning NFS LUNs on the new storage is also a vital step because it directly impacts the performance and capacity of the storage environment where the virtual machines will reside. By appropriately sizing these LUNs, you ensure that there will be sufficient space and performance to handle the workloads of the guest VMs in the new environment, which is crucial for maintaining operational efficiency and performance.

In summary, both tagging the VLAN for live migration and provisioning NFS LUNs are crucial steps that facilitate a successful guest migration to new infrastructure. Proper execution of these steps minimizes risks and enhances the overall migration experience.