In disaster recovery planning, which metric indicates the maximum duration of downtime acceptable by an organization?

Sharpen your skills for the CompTIA Cloud+ (CV0-003) exam. Explore flashcards, multiple choice questions with hints and explanations, ensuring you're well-prepared for success!

In disaster recovery planning, the metric that indicates the maximum duration of downtime acceptable by an organization is known as Recovery Time Objective (RTO). RTO defines the target time set for the recovery of IT and business activities after a disaster has occurred. It is critical for organizations to determine their RTO in order to align their disaster recovery strategies and capabilities effectively.

A well-defined RTO allows organizations to plan and implement the necessary resources and procedures to resume operations within an acceptable timeframe, minimizing the impact on business continuity and operations. When an incident occurs, having a clearly established RTO helps to prioritize recovery efforts and allocate resources efficiently.

Understanding RTO is essential in the context of disaster recovery as it directly influences the choice of backup solutions, architecture design, and personnel training, ensuring that the organization can recover within the acceptable limits defined by business needs. In contrast, other metrics, such as Recovery Point Objective (RPO), focus on data loss rather than downtime, and thus serve different aspects of the disaster recovery strategy.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy